Do I need a permit to replace siding?

It depends on the specifics

Practice varies more here than almost anywhere: some jurisdictions treat re-siding as maintenance and ask for nothing, others permit it so the water-resistive barrier underneath gets inspected while it is visible.

What changes the answer

These thresholds come from the model code and are commonly amended locally, which is usually where people get caught.

Why it matters

Siding is a rain screen, not a waterproof layer — the barrier and flashing behind it are what keep the wall dry. Getting the flashing wrong at windows, doors and the bottom of the wall causes rot inside the assembly that stays invisible until the sheathing is soft, which is typically several years and tens of thousands of dollars later.

Confirm the requirement with the authority that would issue the permit before deciding.

The version of this people actually ask

Do I need a permit to replace siding on one wall?

Often not — partial replacement is frequently within what a jurisdiction calls ordinary repair, and some publish a threshold in square feet or as a share of the wall. Above it you are altering the envelope. The scope tends to grow anyway: opening one wall is how people discover the barrier behind it was never lapped correctly.

Do I need a permit to install siding over existing siding?

Layering is where jurisdictions get stricter rather than more relaxed, and several prohibit it. Going over the old material buries whatever condition it is in, changes how windows and doors sit relative to the new surface, and can trap moisture against sheathing with nowhere to drain. Where it is allowed there are usually conditions about furring, drainage and the state of what is underneath.

Do I need a permit for stucco or brick veneer?

More often than for vinyl or fibre cement, because both are heavier and both are more failure-prone when the drainage plane is wrong. Veneer needs support and ties into the structure; stucco is a system with lath, layers and a drainage plane behind it, and stucco moisture failures are among the more expensive residential defects there are.

Do I need a permit to add insulation under new siding?

Adding exterior insulation while the walls are open is usually a good idea and generally brings the energy code into scope, which is where a permit becomes likelier. It also changes the assembly's drying behaviour — where the insulation sits relative to the barrier decides which way the wall dries, and getting that backwards in a cold climate causes condensation inside the wall.

This is the typical rule, not your answer

This is the typical rule in the United States and not a decision about your property — permitting is run by more than 22,000 separate authorities and any of them can amend the code it adopts, so confirm with your local building department before you start. Put a ZIP in to see what applies in that state, and how to reach the office that decides.

IRC R105.2 exempts ordinary repairs but not alteration of the exterior envelope. Cladding, the water-resistive barrier and flashing requirements come from IRC Chapter 7, principally R703, with additional requirements in wind-borne debris regions under R301.2.